园林工程建设项目的生产过程大致可以划分为四个阶段,即:工程项目计划立项报批阶段,组织计划设计阶段,工程建设实施阶段和工程竣工验收阶段。
The production process of landscape engineering construction project can be roughly divided into four stages, namely: project plan approval stage, organization plan design stage, project construction implementation stage and project completion acceptance stage.
一、工程项目计划立项报批阶段
1、 Project plan approval stage
这个阶段又叫工程项目建设前的准备阶段,也称为立项计划阶段。
This stage is also called the preparation stage before the construction of the project, also known as the project planning stage.
它是指对拟建项目通过勘察、调查、论证、决策后初步确定建设地点和规模,通过论证、研究、咨询等工作写出项目可行性报告,编制出项目建设计划任务书。然后报主管局论证审核,建设部门批准并纳入正式的年度建设计划。工程项目建设计划任务书是工程项目建设的前提和重要的指导性文件。
It refers to the preliminary determination of the construction site and scale of the proposed project after investigation, investigation, demonstration and decision-making, and the preparation of the project feasibility report and the project construction plan assignment through demonstration, research and consultation. Then, it shall be submitted to the competent authority for verification, and approved by the construction department and incorporated into the formal annual construction plan. Project construction plan is the premise and important guiding document of project construction.
园林建设工程
它要明确的内容主要包括:工程建设单位、工程建设性质、工程建设类别、工程建设单位负责人、工程建设地点、工程建设依据、工程建设规模、工程建设内容、工程建设完成的期限、工程的投资概算、效益评估、与各方的协作关系以及文物保护、环境保护、生态建设、道路交通等方面问题的解决计划等。
The contents to be clarified mainly include: project construction unit, project construction nature, project construction category, person in charge of project construction unit, project construction site, project construction basis, project construction scale, project construction content, project construction completion period, project investment budget, benefit evaluation, cooperation with all parties, cultural relic protection, environmental protection Ecological construction, road traffic and other aspects of the solution plan.
二、组织计划设计阶段
2、 Organization plan design stage
工程设计文件是组织工程建设施工的基础,也是具体工作的指导性文件。具体讲,就是根据已经批准纳入计划的计划任务书内容,由园林工程建设管理、设计部门进行必要的组织设计工作。园林工程建设的组织设计主要包括两部分:一是进行工程建设项目的具体勘察,进行初步设计并据此编制设计概算;二是在此基础上进行施工图设计。
Engineering design document is the basis of organizing engineering construction, and also the guiding document of specific work. Specifically speaking, according to the content of the plan task book that has been approved and included in the plan, the landscape engineering construction management and design department shall carry out the necessary organization and design work. The organization design of landscape engineering construction mainly includes two parts: one is to carry out the specific investigation of the engineering construction project, carry out the preliminary design and prepare the design budget accordingly; The second is to design the construction drawing on this basis.
三、工程建设实施阶段
3、 Implementation stage of project construction
在完成设计并确定了施工企业后,施工单位应根据建设单位提供的相关资料和图纸,以及调查掌握的施工现场条件,各种施工资源(人工、物资、材料、交通等)状况,做好施工图预算和施工组织设计的编制等工作。并认真做好各项施工前的准备工作,严格按照施工图、工程合同以及工程质量、进度、安全等要求做好施工生产的安排,科学组织施工,搞好施工现场的管理,确保工程质量、进度、安全,提高工程建设的综合效益。
After the design is completed and the construction enterprise is determined, the construction unit shall, according to the relevant data and drawings provided by the construction unit, as well as the construction site conditions and various construction resources (labor, materials, materials, transportation, etc.), prepare the construction drawing budget and construction organization design. And conscientiously do a good job in the preparation work before the construction, in strict accordance with the construction drawings, engineering contracts and engineering quality, progress, safety and other requirements, do a good job in the arrangement of construction production, scientific organization of construction, do a good job in the management of the construction site, ensure the engineering quality, progress, safety, improve the comprehensive benefits of engineering construction.
四、工程竣工验收阶段
4、 Project completion acceptance stage
根据国家规定,所有园林工程建设完成后,都要按照施工技术质量要求,进行工程竣工验收。在现场实施阶段的后期就要进行竣工验收的准备工作,并对完工的工程项目,组织有关人员进行内部自检,发现问题及时纠正补充,力求达到设计、合同要求。
According to the national regulations, after the completion of all garden projects, the project completion acceptance should be carried out in accordance with the requirements of construction technology and quality. In the late stage of site implementation, the preparation work for completion acceptance shall be carried out, and the relevant personnel shall be organized to carry out internal self inspection for the completed project, and the problems found shall be corrected and supplemented in time, so as to achieve the design and contract requirements.
工程竣工后,应尽快召集有关单位和计划、城建、园林、质检等部门,根据设计要求和工程施工技术验收规范,进行正式的竣工验收。对竣工验收中发现的一些问题及时纠正、补救后即可办理竣工手续交付使用。
After the completion of the project, relevant units and planning, urban construction, landscape, quality inspection and other departments should be convened as soon as possible to carry out the formal completion acceptance according to the design requirements and engineering construction technical acceptance specifications. Some problems found in the completion acceptance can be corrected and remedied in time, and then the completion procedures can be handled and delivered for use.